Foundations
Foundations will be at a depth not exceeding one metre below finished ground and comprising of 600mm wide by 250mm deep in situ concrete. The foundations to be of a size and type adequate for the purpose and shall conform to the requirements of the building inspectorate. Walls to be formed of 100mm concrete block-work up to DPC level internally built off foundation. Cavity filled solid with lean mix concrete to 225mm below DPC level all round.
Substructure Walls
Walls to be formed of 100mm concrete block-work built off foundations up to DPC. Cavity filled solid with lean mix concrete to 225mm below DPC level all round. Cavity to be closed at cills and jambs incorporating DPC all with block-work returned and incorporated insulation and vertical DPC. Cills at floor level closed with extended screen to back of frame, including insulation and DPM.